System not created any procurement proposal even requrment exists

Former Member
0 Kudos

HI PP Gurus,

Scenario is A,B,C are the header material and D is the component material for them. Current stock of material D is 100 nos. Requirements of A, B, C for the month July is 80 nos. But for the next month means August requirement of header materials are 300 nos, but system has not created the planned order or purchase requisition for the material D.

My question is that for fulfilling the requirement of header materials, D material was available in the month of July. But still header requirement is in next month then why system has not create any procurement proposal for the D material. For this time I have suggested to create a manual PO but for the next time user wants to get procurement proposal directly from SAP. Can anybody tell the solution

Thanks in Advance

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member335796
Active Contributor
0 Kudos

Hi,

Can you see the Dependent Requrements for the Component (D) in MD04?

Regards,

Siva

Former Member
0 Kudos

Hi Siva,

If i go in MD04 screen of the material D then i can see the dependent requirments.

former_member335796
Active Contributor
0 Kudos

If so, what is the Planning horizon Maintained? (Check in OPPQ).

I hope you are using the Procesing key NETCH for MRP.

Are you executing MRP with MD02 or MD01/MDBT?

Whether the MRP Type is VB for D?

Regards,

Siva

Former Member
0 Kudos

Hi,

Planning horizon has maintained,

MRP run is background in MDBT , Processing key NETCH and MRP type is PD.

Same scenerio has created in preprod client, in that system created procuremetn proposals. but not in created any planned order or PR in Production client.

muthusamy_sankaran
Active Contributor
0 Kudos

Hi,

pls check if there is stock and producurement type you maintainted or not

Regards,

Sankaran

dhaval_choksi3
Active Contributor
0 Kudos

Hi ACP,

Pls check Planing File Entry also.

Might be Materials are created before the MRP is actived at Plant level.

Regards,

Dhaval

Edited by: Dhaval Choksi on Jul 16, 2008 6:29 PM

Former Member
0 Kudos

Hi Dhaval,

I have checked the planning file entry in MD21. It is not there. is that thing due to which system could not created any procurement proposal. Same thing i have checed in othe materials for that also planning file entry was not created but for that materials system created the procurement proposals

regards

dhaval_choksi3
Active Contributor
0 Kudos

HI ACP,

For Toal MRP / MPS planing file entry required.

but for Single Item multi level or single item single level it is not.

(Because you have already specified which material is required to run for MRP)

So it lot depends on from which MRP trasnection you have run it.

Regards,

Dhaval