there is a product which has to be manufactured in 5 stages. after completion of 3rd stage that particular product has to be sent to a subcontractor for 4th stage and 5th stage. Here in this place PR has to be generated automatically but without use of MRP. Is this possible in SAP? If so explain me how to do

- Pallu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

This can be done with the help of the external operation key in routing(PP) and a subcontracting info record creation.

Please post this question in PP forum and will get immediate response.