Subcontracting Scenario for serialized, Recursive Material.

Former Member
0 Kudos
656

Hello,

  • We are working with SAP R/3 EHP6 enhancement package, IS-Utilities activated.(No DIMP function activated.)
  • We are working with subcontracting scenario for Serialized Material RECURSIVE BOM.
  • We have to give subcontracting PO to vendor with recursive material ( Material number and Serial Number same at time of return.)
    Recursive component sent to vendor against PO created above with Mvt 541.The material will be taken back to inventory instead
    of any PM order/ Refurbishment Order consumption, so that same can be tracked through inventory reporting for further utilization at different sites.
  • Trying to create GRN, using Mvt 101, system throws an error message " Material serial number already entered", this is because
    system trying to post consumption for recursive component with Mvt 543.
  • Please advice how to handle such scenario of serialization, subcontracting, recursiveness.

We have alternate option of not creating PO and just send the recursive material to vendor using Mvt 541 and use report
MBLB to track the material at vendor , and take back to stock with Mvt 542(No taxation scenario) , once repaired and received.
We are using valuation types for material for identification of faulty and repaired material.

Thanks,

Ankush

0 Kudos

Ankush did you find the solution. I am facing the same issue

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Ankush,

Did you find how to manage this scenario ?

Nicolas

Former Member
0 Kudos

Dear Ankush,

With serials you have to use ADSUBCON.

Amnon

Former Member
0 Kudos

Thanks Amnon for reply.

I have mentioned in my message " No DIMP function activated", only "Utilities" Business Function set activated.

I think ADSUBCON will only work with DIMP activated , along with Switch LOG_EAM_ROTSUB2.

If in case, we activate "DIMP" along with "UTILITIES" business function sets, what will be other implication's to existing integral process related to utilities and procurement processes?

Ankush