on 2019 May 29 10:33 AM
Hi guys we provide stock for subcontract 5 Pc and received 3 pc s remaining 2 pc are spoiled (collapse) in sc vendor so what is the next scenario
Hi,
Receive the product to the plant and do the quality test, move the quantity to Quality storage location or Dump it using 551 movement.
Regards
Mahendran P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.