I have created 250 Maintenance Plan thru IP41 T-code, but strategy field is not showing in maintenance plan additional data, moreover maintenance plan cycle field is Enable to change even after the scheduling the maintenance plan, whereas in previous maintenance plan this field is grey and not editable.

Can i mention the strategy in maintenance plan.

moshenaveh
Community Manager
Community Manager
0 Kudos

Welcome to the SAP Community. Thank you for visiting us to get answers to your questions.

Since you're asking a question here for the first time, I'd like to offer some friendly advice on how to get the most out of your community membership and experience.

First, please see https://community.sap.com/resources/questions-and-answers, as this resource page provides tips for preparing questions that draw responses from our members. Second, feel free to take our Q&A tutorial at https://developers.sap.com/tutorials/community-qa.html, as that will help you when submitting questions to the community.

I also recommend that you include a profile picture. By personalizing your profile, you encourage readers to respond: https://developers.sap.com/tutorials/community-profile.html.

Now for some specific suggestions on how you might improve your question:

* Outline what steps you took to find answers (and why they weren't helpful) -- so members don't make suggestions that you've already tried.

* Share screenshots of what you've seen/done (if possible), as images always helps our members better understand your problem.

Should you wish, you can revise your question by selecting Actions, then Edit.

The more details you provide (in questions tagged correctly), the more likely it is that members will be able to respond.

I hope you find this advice useful, and we're happy to have you as part of SAP Community!

View Entire Topic
preetirai1984
Participant
0 Kudos

Hi,

IP41 to create single cycle plan. For strategy use IP01 or IP42. Single cycle plan can't be converted into strategy. So please create new strategy based plan and deactivate the old plan.

You can detach the task list from the existing plan and converted to strategy based and use in new strategy based plan.

Regards,

Preeti