Dear Guru,

Can any body tell me what is the different between strategy 20 and 81

Thanks!

Regards,

Nilesh

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Nilesh,

The difference is that you wont get directly the production proposals (Planned orders/production Orders) when the sales orders are created with Strategy 20 material, you need to run MD50 or MD02 to get the proposal. Once Planned orders / production orders are created, you can change the quantity or dates and the orders can be closed independent of Sales order.

In Strategy 81 you get the planned order created when sales order is created, also you cannot change the quanity of the order and setting status of the production order is drived from the sales order item status.

Regards,

Prasobh

Former Member
0 Kudos

Hi Mr. Prashob,

I am doing mfbf against plan order system giving me error

"Planned order (46) is only allowed for make-to-order production"

My strategy of material is "81"

From witch t-code I have to go for back flush.

Nilesh

former_member196398
Active Contributor
0 Kudos

Nilesh,

Please close this thread if answered and we can communicate on the thread you have created for MFBF problem.

Regards,

Prasobh