Hi,
How can I stop to create certificate in QC51 before Inspection lot creation for a material GRN through PO.
Hi Soumy,
The inbound certificate receipt functionality is enabled in the material master QM view by the settings of 'QM in procurement' and the 'QM control key'.
So please uncheck the 'QM in procurement' checkbox in the material master to de-activate the certificate requirement for a material.