Former Member
0 Kudos

Hi All,

ours is a project based company and we dont have plants as we are not into any type of production.

we have registered offices at 14 states in India. At present stock is valuated for each project and all values will be accumalated and shown in balance sheet.

we have PS also.

in this type of scenario how can we suggest plants in SAP and valuation.

please suggest me.

thanks in advance.

shashi

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Shashi,

You can go for single project plant, which can have 1 storage location per project. Also you need to suggest one profit center per project to view the balance sheet seperately per project. Also you need to use project stock Q for valuating the project stock.

Thanks & Regards

Sanjay

Edited by: Sanjay Marathe on Mar 26, 2010 5:52 AM

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi Shashi,

You are absolutely right. From taxation perspective you need to have 14 plants which is 1 per business place. Further you can have multiple project linked to same plant if it belongs to the same state.

Thanks & Regards

Sanjay

govind_gogate2
Active Participant
0 Kudos

Dear Shashi,

1) ours is a project based company and we dont have plants as we are not into any type of production.

Ans - It is not necessary that you have to have production to create a plant.

2) At present stock is valuated for each project and all values will be accumalated and shown in balance sheet. -

- How you valuate plant for each project? What organisational structure elment you use to do so?

3) Based on other details, even if you are having PS, you can create plant to valuate the material. You can assign the plant to the project created. I assume that you are buying material for the project. All material movements are happening with respect to the project. If you are having document splitting & want to track project wise profitability & receivable / payable & other balance sheet items, then it is better to create plant and profit center for every single project.

The material valuation should be at plant level relevant to each project to track better material movement & valuation.

regards,

Gov

govind_gogate2
Active Participant
0 Kudos

Dear Shashi,

1) ours is a project based company and we dont have plants as we are not into any type of production.

Ans - It is not necessary that you have to have production to create a plant.

2) At present stock is valuated for each project and all values will be accumalated and shown in balance sheet. -

- How you valuate plant for each project? What organisational structure elment you use to do so?

3) Based on other details, even if you are having PS, you can create plant to valuate the material. You can assign the plant to the project created. I assume that you are buying material for the project. All material movements are happening with respect to the project. If you are having document splitting & want to track project wise profitability & receivable / payable & other balance sheet items, then it is better to create plant and profit center for every single project.

The material valuation should be at plant level relevant to each project to track better material movement & valuation.

regards,

Gov