Stock requirement list & MRP list

Former Member
0 Kudos

Dear All ,

What is the difference between Stock requirement list & MRP list ?? anybody who could explain in detail ??

Regards

Sarfraz

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sarfaraz,

The MRP list always displays the stock/requirements situation at the time of the last planning run and it also provides a work basis for the MRP controller. Changes that are made after the planning date are not taken into consideration, so the list is static.

In the stock/requirements list, the most up-to-date stock and requirements situation is displayed.

The main difference between the MRP list and the stock/requirements list is that each time the stock/requirements list is called up, the system selects the various MRP elements and displays the most up-to-date situation. You thus always see the current availability situation of the material in the stock/requirements list. Changes that are made after the planning date are displayed directly, so the list is therefore dynamic.

Comparison

The screen layout of both lists is basically the same.

The system automatically runs the rescheduling check directly when both lists are created and puts forward rescheduling proposals.

The number of exception messages displayed in each list is roughly the same. The only difference lies in the fact that, due to the nature of the list, no exception messages can occur for newly planned MRP elements in the stock/requirements list.

Directly after the planning run, both lists contain the same information. As soon as a change relevant to MRP is made, the system updates the information in the stock/requirements list.

As stock/requirements lists are subject to change, they cannot be set with a processing indicator.

Regards,

Pradeep

Answers (4)

Answers (4)

former_member539472
Contributor
0 Kudos

The stock/requirements list displays the currently valid stock and requirements situation, that means, the system always updates the MRP elements when you access the list. The MRP list, however, displays the stock and requirements situation at the time of the last planning run and does not take into account any changes after the planning date.

[Definition of the MRP List]

The system creates MRP lists during the planning run according to how you set the creation indicator. These lists contain the planning result for the material. The MRP list always displays the stock/requirements situation at the time of the last planning run and it also provides a work basis for the MRP controller. Changes that are made after the planning date are not taken into consideration, so the list is static.

MRP lists are stored in the system until they are either deleted manually or replaced by new lists from a subsequent planning run.

[Stock/Requirements List]

In the stock/requirements list, the most up-to-date stock and requirements situation is displayed.

The main difference between the MRP list and the stock/requirements list is that each time the stock/requirements list is called up, the system selects the various MRP elements and displays the most up-to-date situation. You thus always see the current availability situation of the material in the stock/requirements list. Changes that are made after the planning date are displayed directly, so the list is therefore dynamic.

Stock/requirements lists are not saved in a fixed state in the system, but are subject to change and only exist in the working memory.

[Comparison]

The screen layout of both lists is basically the same.

The system automatically runs the rescheduling check directly when both lists are created and puts forward rescheduling proposals.

The number of exception messages displayed in each list is roughly the same. The only difference lies in the fact that, due to the nature of the list, no exception messages can occur for newly planned MRP elements in the stock/requirements list.

Directly after the planning run, both lists contain the same information. As soon as a change relevant to MRP is made, the system updates the information in the stock/requirements list.

As stock/requirements lists are subject to change, they cannot be set with a processing indicator.

Former Member
0 Kudos

hi

stock requirement list is current status of stocks list and MRP list is static list which shows result of last MRP run

Regards

Pravin

Former Member
0 Kudos

Hi,

MD04 is a dynamic one. After MRP run if any user created sales order or demand by MD61, it will get update in MD04.

But in MD05 , demand created after MRP run will not get update. So If you want to see result of MRP run after some time or days, you can see in MD05.

It is static one.

Regards,

Dharma

former_member335796
Active Contributor
0 Kudos

Hi,

Stock/Requirements List - MD04 is a dinamic list.

in this upto the minute information can be accessed.

MRP List - MD05 is a Static Lict.

Here the information captured is of last MRP run.

Till the next MRP Run, the information in this report will not be change.

Regards,

Siva