Standard cost estimate period

Former Member
0 Kudos
1,531

  1. Can you please let me know in which period do we need to perform cost estimate and 1. Markℜlease functionality .
  2. How many time can per perform cost estimate in a year. Is it yearly or can we even perform monthly or bymonthly or quarterly or half yearly
  3. Is there there any GL posting if I per mark and release
    1. Performing mark & release 1st time for the material. i.e. in 1st year
    2. Performing mark & release 2nd time for the material. i.e. in 2nd year.
View Entire Topic
Former Member
0 Kudos

Thank you for the information.

I have 2 material; For only 1 material I have mark and release one material which was successful for the period 8/2018. I forgot to add Material 2 for mark and release. Now If I am doing again for Material 2 getting error message

*************** Summary : *********************

Message no. CK790

and

Of 0 materials, 0 cost estimates were updated successfully

Message no. CK705

how to fix this

Qi_Liu
Product and Topic Expert
Product and Topic Expert
0 Kudos
check the costing 2 view in master data, may be material 2 has already been released.
Qi_Liu
Product and Topic Expert
Product and Topic Expert
0 Kudos
or if you are using CK24, make sure the date is in next period. Suppose today is 2025.01.16, then you need to change the date in CK24 to next period date Eg 2025.02.01