on 2015 Sep 15 2:46 PM
I have created a cost estimate using CK11N and marked and released it.
I noticed that for one of the lower level subassembly, the system has
recalculated the standard and created a cost estimate for it with costing
status "KA". For this subassembly, there was already a released (Status
"FR") cost estimate from the beginning of the year with different
standard.
My questions are :
1)Is there a way in CK11N to tell the system to use released cost estimate
for the lower level subassembly instead of recalculating cost estimate?
2)Why didn't the system mark and release cost estimate for the lower level subassembly
when I released the cost estimate for the final assembly. I have seen it happening when I used CK40N in the beginning of the year.
3) Is there a report to identify what caused the change in standard for the
lower level subassembly? I can go through CK13N report side by side for the
"FR" cost estimate and "KA" cost estimate. But it will be
time consuming.
Thanks
Sanjiv
Request clarification before answering.
Hi Sanjiv
Ans to Q1 : Make use of transfer control for this requirement.
Ans to Q2 : Ck40N has this functionality but in case of Ck11N you have to mark and release all the materials using CK24
Ans to Q3 : I am not on the sap system right now but I if I am not wrong you can use ck79_99 for this requirement. Kindly check once and revert.
Regards
Rajneesh Saxena
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
117 | |
8 | |
7 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.