on 2012 Feb 09 12:32 PM
I have created two Depot (6011,6013) and one plant(6010). Now, Sales order has created in 6011 and production will be carried on 6010 plant. I want to use Special procurement key for this. Can anybody please suggest what will be the exact settings for this scenario to be executed?
Hello,
You can define & use Spl Procurement Key with Stock transfer from 6010 to 6011.
Spl Procurement Key definition in Plant-6011 in SPRO as below:
Plant - 6011
Spl Proc Key- 40
Proc Type- F
Special procurement - U (Stock transfer)
Plant - 6010 (Prod Plant)
Hope it will help.
Rwgards,
Anup
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
You've two Depots (From where you'll raise Sales Orders), so need to create a Stock Transfer Spl Proc Key in both Depots/Plants with Production Plant as 6010.
Then need to assign respective Spl Proc Key in particular Material Number in Depot. e.g. Key-40 for Depot-6011 & Key-40 for Depot-6013. Spl Proc Key definition is @ Plant Level.
Now, whenever there's a sales requirement in Depot, a production requirement will flow to Production Plant-6010 after MRP in Depot/s.
Hope it's clear.
Regards,
Anup
User | Count |
---|---|
92 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.