Hi

How can be set up that while MRP run that the contract item is automatically assigned to a requisition item as the source of supply?

Accepted Solutions (1)

Accepted Solutions (1)

former_member197616
Active Contributor
0 Kudos

Hi,

Please create a source list for the material in that plant with that aggrement.In the source list tick mark the MRP relevant and fix the vendor.This will help in finding the suplly source determination.Prior requirement is info record.

Regards,

Answers (2)

Answers (2)

former_member581212
Active Contributor
0 Kudos

hi,

The requirements should match following points:

1. Maintain the contract as a source in the Source list wid the FIX source indicator and MRP relevent indicator...

2. Do enter the proper VALIDITY PERIODS, other system will not take this source into consideration while running MRP...

Hope it helps..

Regards

Priyanka.P

Former Member
0 Kudos

Hi

Maintain a source list in ME01.

In this for a particular material, enter the relevant details and check the fix vendor and MRP relevant.

It will assign the source while doing MRP run.

Check it out.

Regards,