I have the following scenario:

I have valuated project stock.

I have contracts created with account assignment Q for wbs element.

I create PR's for those web elements. In source determination it is required that it considers only contracts with the same account assignment.

Is this possible???

Thanks,

Accepted Solutions (0)

Answers (1)

Answers (1)

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

In source list(ME01) - you can maintain your contract number  but to copy account assignment Q with related G/L account during creation of purchase requisition from contract- you need to go for development as in standard when you will create purchase requisition(ME51N) from contract – you need enter manually account assignment Q , G/L account number with contract number.

Regards,