Hi,

I was trying to transfer the activity quantities booked in processs order to the SKF created by establishing the link. The list of transactions done are:

Step 1

KK01 with LIS: creation of SKF linked to with Info Structure/shop floor control/operation/actual execution time.

Step 2

kp46 : Entered cost center/activity type/skf and entered planned values with Dist Key as 1

step 3

COR6N: here confirmed the activity

step 4

KVD5: Transfer of Acitvity Dependent SKF

Here we have error "No statistical key figures with variants were found for object ATY N001/PRODUCTION/HRS in fiscal year 2007 for LIS reference"

How to solve this issue or any other settings are required to collect data directly from activity type through SKF to the cost center.

Bye,

Ramesh

View Entire Topic
Former Member
0 Kudos

KVA2.. here you need to assign SKF and variant for each cost center. Variant is the link between SKF for each CC and LIS.

Regards,

Chendurapureddy
Explorer
0 Kudos
how we can do in s4 HANA please suggests me give an explanation