This may be a basic question, but could you please explain in which situations production orders would have to be created manually (using t-code CO01), instead of creating them via the MRP run?
Thanks in advance for any replies.
Hello,
It depends upon how good you are in planning and setup of MRP run?
Ideally there should not be requirement to create manual production order without planned order reference. However there is no prefect world in rush order scenario, material scrap, customer requirement changes or reject in quality inspection, manual production order comes in picture.
There are few clients which I have seen that they do not allowed manual creation of production orders with same order type to rack the KPI of planning/planner.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.