on 2023 Oct 13 9:07 AM
Hi Gurus,
Could you please help me to resolve the below issue ?
If the amount in the shipment is more than 50,000 means I cant able to create the shipment cost document generated the service PO it was popping release strategy.
I believe that is standard functionality. could you please help me to resolve this ?
If the shipment amount is more than 50,000 it should generate the Service PO in the shipment cost document! - Please help me.
Thanks & Regards
Madhu G
Hello Madhu, It appears that the release strategy is active for the service purchase order, please check the following:
1) Ensure that any characteristics are maintained in CT04.
2) Check the class in CL02.
3) Review the release strategy configuration by following this path in SPRO: Materials Management -> Purchasing -> Purchase Order -> Release Procedure for Purchase Orders -> Define Release Procedure for Purchase Orders.
4) Verify the release strategy on the service purchase order header, as it needs to be released before creating shipment costs.
Thank you!
PS: If you find this answer resolves your issue, kindly close the thread upon resolution and consider giving a reward!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
8 | |
7 | |
4 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.