Setting material status automatically

Former Member
0 Kudos
374

Can I set material status (e.g. End of life) automatically ? I mean can I schedule any standard program which will set this status by calculating different parameters.

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

SAP does not have such standard program, as end of life of a material is not usually automatically reached after a certain number of days, months or years. It depends on market situation .

Further the the material status is something you define yourself, so SAP cannot know which status it should set.

You would have to develope a report to your own needs and update the material master then with e.g. a batch input.

I hope you did not mix end of material life with stock that has reached shelf life expiration date.

Former Member
0 Kudos

Thanks ........Can you also explain what is general logic of 'End of Life' staus ?