I have been trying to set up the controlling area using t.code EC16. When I try to copy I get an error that the "Objects were not selected as a connected list".

Can someone explain or tell me as to how I should go around configuring the controlling side using this t.code.

I copied the company code using t.code EC01 and then went on the copy the chart of accounts using t.code OBY7.

I really do not know how to select the objects as a connected list. I am very new to SAP.

Thanks in advance for your time in this matter.

Mahesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi first u have to maintain controlling area. then u have to activate the cost center in controlling area . if it comes to profit center u have to set up the controlling area.

goto enterprise controlling>pca->basic settings----


> controlling area.