Dear All,

We are crating Service PR via Network service activity. The budget is coming from IM to WBS.

The issue is while the user is trying to create a PO with reference to a PR he is getting budget issues but there is enough budget for that WBS

When i have checked the report S_alr_87013558: The available balance is showing less. We have not booked the actuals against that wbs. It is deducting from the commitment values and shows the available balance low

Please see the screenshot of report capture-1.png

Please help with this

Thanks & Regards

Praveen

View Entire Topic
BalasubramanianAP
Active Contributor
0 Kudos

Hi, Commitment means PO is made with this budget. This is not actual but it is called commitment. You can check with S_alr_87013533 report to see the detailed commitments made with this WBS.

You can also check with detailed report such as GR55 with report group 6P01 for this WBSE whether any PO(commitment) is created or not by drilling down.

0 Kudos

Hi Bala,

My issue is in the report system is available budget is showing Budget - Commitment cost = Available

But actually it should be Budget - Actual = Available

Thanks