on 2022 Jan 31 7:01 AM
Dear All,
We are crating Service PR via Network service activity. The budget is coming from IM to WBS.
The issue is while the user is trying to create a PO with reference to a PR he is getting budget issues but there is enough budget for that WBS
When i have checked the report S_alr_87013558: The available balance is showing less. We have not booked the actuals against that wbs. It is deducting from the commitment values and shows the available balance low
Please see the screenshot of report capture-1.png
Please help with this
Thanks & Regards
Praveen
Request clarification before answering.
Hi, Commitment means PO is made with this budget. This is not actual but it is called commitment. You can check with S_alr_87013533 report to see the detailed commitments made with this WBS.
You can also check with detailed report such as GR55 with report group 6P01 for this WBSE whether any PO(commitment) is created or not by drilling down.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
9 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.