hi dudes

I want to send some equipments outside of company because of a service(e.g. Calibration), I created a PO or PR for service (Item category D) , entered sommething in short text but where I can add name of equipments and I want to send them out???

there is no place for them in PO screen. what can I do?

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi,

Its best to use Subcontract option for sending material to oust side.

Regards,

Andra

Former Member
0 Kudos

Why can not you use the Item Text fields available for the purpose?

Regards

Former Member
0 Kudos

if i enter material or equipment in PO it means that i want to bye that material from vendor... isn't it?

Former Member
0 Kudos

Use non valuated material with serial number. And put serial number as equipment number. By which you can trace the equipment else you if you send more than 1 same equipment you will loose tracability...

Former Member
0 Kudos

Hi,

if Material is not in stock,then you have to create a new Non-valuated material for equipment.

Thru reversal create stock for the material,then send material to vednor for service.

when material recived,done G.R. & issue the meterial.

Regards

Pavan

Former Member
0 Kudos

you need to create a BOM with recursive indicator marked that is you need to enter the parent material and item material as same.

becuase you are sending it to vendor for job work

create the po for subcontracting that is with item category L