Hi Expert,

I m creating Internal order T.Code KO04 

in Costing Variant PC02

Dates Tab

Costing Date From 01.01.2013

Costing Date To     10.01.2013

Valuation Date :     15.01.2013

Message showing select costing variant with date control after save

kindly help me

Kind regards

Pranav

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

yes as i said that first check the the period validity from configuration and then run ko01 for creation of internal order

pranav_gupata
Participant
0 Kudos

yes sir i did Ko01 but costing model not coming....

Order Type KFLD

Order HFD_067

Company Code xxxx

BA -xxxx

Plant xxxxx

Object Class - Investment

actually i want to calculate the cost of  DIE Manufacturing so reason i want to capture the cost coz in our system Die manufactring related data not there and client want DIE manufactring cost.. so i choosed Internal order... in internal order i ve to configure so guide me if i click on costing button then screen like Choose Planning form, once i go n click on that system asking costing model , when i press f4 no costing model is there.. so where i ve define costing model...

thx

pranav

yr qucik respose is highly appreciated...

Former Member
0 Kudos

Choose some standard order type

Go to SPRO check Define order type and check the oreder type KFLD

former_member348872
Active Contributor
0 Kudos

Cofigure Date control in transaction OKKR.

pranav_gupata
Participant
0 Kudos

now if m doing click on planning Form , system asking Costing Model where i can define costing model... in our system no costing model A0001

plzze help me ...

Former Member
0 Kudos

1. Please check the Period validity of costing variant first

2. select costing variant by F4 to avoid the mistake

3. create new internal from KO01

pranav_gupata
Participant
0 Kudos

Only one Costing Variant PC02 is there by default only one variant is there.... n where i can see the Costing Variant... only

in OKKN screen

Tell me wht should i do ... m stuck now... if i go create Internal order Ko01 there would be any problem...

let me knw.

Thx...

narasimhulu_konnipati
Active Contributor
0 Kudos

No, do not create IO. First check the date control in OKKN by double clicking on PC02.

Is it Month, or Period or Current Cost estimate dates......................?

Just check.....

Thanks