cancel
Showing results for 
Search instead for 
Did you mean: 

Segregation of cost of material and process to different WBS

sunil_yadav2
Active Contributor
0 Kudos
170

Hello All,

We have implemented the PP & PS for Assembly Processing. In this process when we are running MRP and generating reservation this will create planned order than this will converted to Production order. So after confirmation of this production order Cost of Raw material and cost Process execution is coming on single WBS.

Where our requirement is to segregate this cost to different WBS as Raw Material cost should come under Material WBS and Process cost should comes under Process WBS. so Project reports can show transparency of actual cost occurred.

currently we have CJI3 to check actual cost and this will manually transferred to required WBS using KB11N.

Please guide for Segregation of cost with in this process so we don't have to do manually steps to transfer this cost to different WBS.

Thanks

Sunil

Accepted Solutions (0)

Answers (1)

Answers (1)

sunil_yadav2
Active Contributor
0 Kudos

Hello All,

Please guide us for segregation of cost to different WBS. We are getting all material and process cost on one WBS to which we assign material.

please tell me the process for segregation of cost of material on different WBS and Proces cost on different WBS.

Thanks

Sunil

sunil_yadav2
Active Contributor
0 Kudos

Hello Experts ,

Please guide me how to segregate this cost to different WBS.

Thanks

Sunil