on 2010 Dec 24 11:16 AM
Hello ,
Kindly let me know the steps to plan secondary cost element with category 42.
Thanks
Hi Muscan
you can plan only for 41 category of secondary cost elements
42 and 43 can not be planned manually..
42 - is linked with assessment cycle (KSUB) and 43 is linked with activity types
Regards
Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Muscan,
You cant plan directly the Secondary Cost Elements. Create a Plan Assessment:KSU7 and Execute Plan Assessment: KSUB.
Regards,
Balaji Bhonsle.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You cannot plan secondary cost elements ... Secondary cost elements are used to allocate costs from one ost center to another...
They cannot be planned...... Plan only primary Cost Elements.
Regards
Sarada
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.