Hi,

Please i want know the impact of change in screen sequence in MRP type.

this screen sequence is used for display the header tab in md04 report , other than this is there any impact.

can we change predefine screen sequence to our own.

thanks.

as

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Screen sequence defined in OMIO is for the display of the header details in the evaluation of the planning run as per the MRP type in OMDQ there is no other impact of that.

Regards,

R.Brahmankar