scrap quantity to be minus with operation sequence is not check in co11

Former Member
0 Kudos
80

hello!

PP experts

i have problem in confirmation of production order.

suppose i have production order of 15 qtys.with four operation to be confirmed (co11).

operation qty.yield srcap qty.

0010 1 5 0

0020 14 1

0030 14 0

now, in 0020 operation i have 14 yield & 1 srcap quantity & when i go for 0030

operation for confirmation it will show the default quantity of previous operation,0020 qty. i,e 14 qtys.but if i put the quantity 15 in this operation (0030)

its allowing to confirmed 15 qtys. because the plan qty is 15.but i want to minus the 1srcap qty. from 15 plan qty. & system should allowed only 14 qtys

(15-1=14) for confirmation.plus i want the flexibility of operation sequence not to checked.

i set operation sequence - error when operation sequence is not adhered to in OPK4,its minus the scrap qty. but not allowing the flexibility of operation sequence

confirmations.

please send me the setting for the above query in the confirmation (co11)

regards,

mangesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

The same question was asked few days before by MR Gowri Sankar. The same question you are repeating

check in OPKP Production scheduling profile in the confirmation Tab

Enable the check box Adjustment quantities in order to actuals and then try

in CO11n.

Also you need to set the overdelivery tolerance as warning message in opk4.

Regards,

nandha

Former Member
0 Kudos

sorry,

i want to carry out the conf. through co11 only.

in opk4 setting not giving the proper results

regards ,

mangesh