Goods Issue to Scrap Process:

Normally we do Gi for Scrapping with 551 Movement Type. Based on the Material Document created, we create a TO w.r.t that Material Document. The IM stock reduced immediately. but the stock at WM level still not removed. If we confirm the TO, then the stock will be removed and stored in a separate Storage Type or Storage Bin which is meant for Scrapping purpose.

Now when we check the stock levels both at IM and WM level remains the same. At IM Level (MMBE), it wont show you the exact location of the material but it will show you the total available quantity. but when we look at WM Level (LS24), it will show you the quantity at Bin Level.

My question is:

What is the procedure for this scenario:

If I done the same above scenario, the scrapped quantity should not show when a user executes MMBE transaction. It should show in LS24 Transaction.

How to do this.

Regards,

View Entire Topic
pataselano
Active Contributor
0 Kudos

For solution, please check following SAP note: 1871525 - Correction cases of stock inconsistencies between IM and WM.