Hi,

We have issue like as below.

We are sending assembly component to the vendor he will assemble the component and sends back single material as semi finished

Process flow is Create Sub con PO> Issue material against Sub con PO> Create challan> Receipt material> Reconcile challan>

But challan shows incomplete as child componenet shows as scrap generated which is showing as due for reversal

Why scrap is showing in challan how it avoided.

Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member187989
Active Contributor
0 Kudos

Check BOM Whether any -ve qty in child components ??

Former Member
0 Kudos

Hi Jayanth,

No we don't have BOM but the scrap is getting generated because of component scrap is maintained in Material master.

Ans same is appearing in J1IFR Challan as

How we can avoid being scrap apeareance in J1IFR Challan

Regards

Former Member
0 Kudos

Hi

you can do subsequent adjustment entries to get the residual finished / child material from the S/C vendor .then you can able to reconile .

regards