on 2006 Nov 25 7:32 AM
Hi friends,
I have got one more problem. I am doing my confirmation CO11 for my production order. While doing so , i am entering yield quantity as 100 and scrap quantity as 10.
Then i am doing my goods movement, it is posting only yield quantity as 100 in movement type 101 but it is not bringing my scrap quantity 10 under mov. type:551.
Even i have tried in MB1A, mov.type 551 ( I have entered my production order and cost center), the system in not bringing the scrap quantity 10 ( what i have entered in confirmation) automatically. It is expecting the user to key in again.
Please clarify any config required ?
Thanks
Senthil
Request clarification before answering.
Hi
I won't think system will automatically post 551 document from the production order confimration, once the scrap qty is entered. This qty is considered only for the costing purpose of the production order. The automatic posting of the scrap is available in QM while taking usage decision.
Regards
Mani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
39 | |
8 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.