Scheduling the requirement quantities on different dates for different vend

Former Member
0 Kudos
54

Dear Gurus,

We have requirement of generating the shcedule line on different dates

in case multi supplier. The part is supplied by 3 different supplier when executing MRP the system generated schedule line on same date for each supplier,

however the business requirement is not to receive all material on same

date. But to receive all the requirements on the 3 consecutive days say for 3 different vendors. We have maintained Quota Arrangement for splitting the requirements order quantity.

Pls suggest the configuration / Material master changes we need to make for the same.

Regards,

Pradeep Santara

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

If you want different dely dates for each supplier, you maintain different planned dely time in supplier specific inforecord for that particular material.

Hope this will solve your problem.

Reward if so

thanks & regards

sri.