Scheduling of KKAO (Calculate WIP)

Former Member
0 Kudos
336

Dear all,

does anyone know whether i can schedule KKAO (Calculating WIP) in the way that it will automatically input the period and fiscal year data based on the current date of the system? I know that it has a run in background option, but I need to schedule this as a weekly job so it is best if automation is possible and input from user is not required.

Thanks and Regards

Yiming

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Yiming,

If you wish to schedule this process (either with or without SCMA) to achieve a change in the period without user maintenance it is best to use one of the background programs and set variants.

For example using SE38/SA38 use program SAPKKA00BG set your selection parameters and when saving the variant choose Environment -> "Main. Sel.Variables" this will bring you to transaction STVARV which enables you to set a variable for the selection screen.

If you look up more details on STVARV this I think will help you.

If you are using schedule manager and require logs make sure to use the correct program (see sap note 421231).

Regards, Elaine

Former Member
0 Kudos

Hi Elaine,

thanks for the details, will try out the suggestions and update again.

Regards

Yiming