on 2021 Nov 15 7:19 PM
Hi All,
I have created Scheduling agreement with LP.
MRP run schedule lines generated & seen in ME38 .It has multiple schedule lines . I have created output LPET .but when i see the output it displays all the schedule lines with dates & qty.
Now i want to manually release the individual schedule lines one by one to the supplier as an when i want.
I am not using FRC or JIT
Please guide how to achieve this?
Hi gzanolet
I ran the MRP which generated PR i assigned the SA in the PR ,then try to generate the Schedule lines in ME38 referring to PR but the option is in display mode, can you guide on how to create Schedule lines refering to PR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I do not have access to the system now, however, schedule lines can be created by converting PRs using
a) ME38: go the the delivery schedule list for the SA item, then Sch. agmt. schedule > Create w. reference > To purchase req. and/or
b) ME57 or ME58 if the purchase requisitions have been assigned with the scheduling agreement item.
Please, have a look at Creating POs, Schedule Lines, and RFQs from Requisitions.
Regards
Gianmarco
Hi ,
Mistake from my end, i was trying to assign the PR in the initial screen itself which is not possible .Need to go inside the ME38 screen then click on Delivery schedule option ,then at the top select Scheduling agreement/Release a window pop up appears where we need to enter the PR no & hit adopt ,schedule lines will be generated with output, if condition records are defined in MN10