Scheduling line delivery date automatically post to the next day

Former Member
0 Kudos

Hi Friends,

When creating sales order, the delivery date under schedule line shows automatically to the next day to the second line. We used to see only one line with delivery date of today. How to fix it?

Thanks,

Linda

View Entire Topic
Former Member
0 Kudos

Hello,

To define the delivery date, system takes into consideration the below activties workload time according to system settings in SPRO :

1- Material availibality date

2- Loading date

3- Good issue date

4- finally delivery date.

You can overwrite these data manually by : Double click on the schedule line, choose shipping tab, then enter today date for all activities.