Scheduling : Backward

Former Member
0 Kudos
71

Hi all ,

I have FG contains SFG

I am doing backward scheduling .

after MRP , in MD04 the planned order dates and time r as follows :

For FG : date time

Order finish : 30.03.2008 17:30:00

Order start : 23.03.2008 12:50:00,

and for SFG actually the dates the system is giving :

Order finish : 23.03.2008 17:30:00

Order start : 23.03.2008 10:30:00,

Now the requiremnt here is Order finish of SFG should be one day before , that is 22.03.2008 , i am trying with Sch margin Key as :

Flt before prodn : 1 day & float after prodn : 1 day , what i have to use so that i can get one day Gap ?

Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Try with scheduling margin key for SFG with 1 day as float after production.

Former Member
0 Kudos

Hi,

With float time you can not achieve this.

Because if you add float after 1 day in SFG, including this float system will show order finish date on 23.03.08

Use lead time offset.

For FG in CS02, item detail screen, enter lead time offset for SFG.

Enter -1 day (minus 1)

Minus means item required before the start date.

Plus means item required after the start date.

Regards,

Dharma