on 2007 Dec 18 8:53 AM
hi,
For LP-document type scheduling agreement how GR is made?(with ref to).
EXPLAIN THE FLOW.
Rgds
raja
Dear Raja,
In case of scheduling aggreement GR is made with reference to Schedule lines.Infact GR cannot be posted prior to schedule lines/ Delivery Dates.
Incase of LP types scheduling agreement , it is transmitted to vendor when saved in the system
If useful reward points,
Vivek Maitra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Scheduling agreement is a PO itself with a validity period.
You need to maintain only delivery schedule.This will generate schedule lines and then u can do GR against the scheduling agreement.
Reward if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
GR is made wrt delivery schedule of SA
Thanks
suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If u have maintained scheduling agreement then u would have maintained delivery schedule to it.
suppose for one scheduling agreement for 400 quantity u have maintained 4 delivery schedules of 100 quantity each, now these delivery schedules will reflect in MD04.
when u do MIGO, u do it with respect to the Scheduling Agreement No. and if u enter quantity as 100 the particular delivery schedule is fulfilled and u cannot c it in MD04.
Note:-In Scheduling Agreement u cannot do MIGO if the MIGO date is earlier than the scheduling agreement date.