Hi,

Can anyone please help me to understand what is the difference between Scheduled and Pool/Rqmts. in CM22. and how the values get derived in both.

I have attached the screenshot for a better explinatation.

Regards

Tejas Khanna

View Entire Topic
0 Kudos

Hello,

Scheduled capacity requirements generated by operation in planning period and pool/req is pool of orders/operations are still to be dispatched in planning period.

Pooled capacity can be assigned to several workcenters so it is nothing but available capacity in several workcenters. Pooled capacity is a group or setup personal/Labours who are engaged to work in multiple workcenters.

however workcenter capacity can be derived from operating time, capacity hrs, utilization and no of indiv. cap. workcenter.

hope it clarifies..

thanks,

NeeDi