Schedule using graphical board CM30

Former Member
0 Kudos

Hello gurus,

I have created a maintenance order and inputted 10 hours in the operation. I do not want the system to auto schedule the order and hence remove it from the customizing setting of scheduling and control key.

We are using graphical board to assign the job to the employees who are assigned to the work center thru HRMS link. After we assign the job to the employees the same date is not updating in the maintenance order under scheduled start date, start time, end date and end time.

So my question is how to achieve this??

Requirement:

Once we assign the employees using CM30, we need the same date and time to be updated in the maintenance order header screen as well as operations tab.

Regards,

Smart Kumar

Accepted Solutions (1)

Accepted Solutions (1)

S0022314014
Active Contributor
0 Kudos

I believe this thread has the same question that you raised in one of your previous threads:

And please also read the following as being an active member of the SCN, you must update the threads which were completed:

Former Member
0 Kudos

Hi Savas,

Requirement mentioned of updating the date and time is not yet answered.

Regards,

Smart

Former Member
0 Kudos

Hi Sava's and Gurus,

Please help.

I have closed all my previous queries.

Regards,

Smart

sunil_mundhe3
Contributor
0 Kudos

Basic Fin. Date should not be in Past, then Only System determines

1. Schedule Start Date

2. Schedule End Date

&

3. Earliest start date

4. Earliest finish date

This is for Forward scheduling Type, not sure about backward?

Former Member
0 Kudos

Hi Sunil,

Thanks. I checked this.

The earliest start date, time, end date, time does not get updated even after scheduling using cm30.

The dates are updated in the requirement assignment in the operation tab.

Thanks by the way.

Regards,

Smart

Answers (0)