Schedule next operation automatically

former_member225891
Participant
0 Kudos

Hello,

In CM25 I will be scheduling operation 10 in the order. Next operations 30, 50 in same order should be scheduled automatically. What setting is needed to achieve this?

View Entire Topic
rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Customizing maintenance of the strategy profile (Transaction OPDB) set indicator of Consider operation sequence in the order.

Please refer SAP consulting note 496852 - Operation sequence for dispatching

Best Regards,

R.Brahmankar

former_member225891
Participant
0 Kudos

Dear Rupesh,

My profile is already set with the indicator, still only first operation getting dispatched. Als there is phase relationship as FS is maintained in master recipe.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please use transaction CM29 with standard profile like SAPPI_G001 for process orders.

Here, the program logic determines the predecessor/successor that

◦is relevant to scheduling (control key),

◦generates capacity requirements (control key),

◦contains capacity requirements according to the standard values.

Best Regards,

R.Brahmankar

former_member225891
Participant
0 Kudos

Hello Rupesh,

I have tried with CM29 with the profile you mentioned. Still only selected operation is getting dispatched. Is there any trick I am missing during scheduling?

former_member225891
Participant
0 Kudos

Hi Rupesh,

Is this possible at all? If yes what is missing could you please let me know.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

It should work with overall profile like SAPPI_G001 , SAPPI_G004 and SAPPI_G002

The operations in a process order should be relevant to capacity planning. The duration of an operation is however determined by the lead time scheduling of the phases.

Please check the phase relanship and control key for scheduling and capacity planning.

Best Regards,

R.Brahmankar