Schedule Line Item Catagorey In Strategy 40

former_member261747
Contributor
0 Kudos

Dear Experts

                       What should be schedule line item catagorey in Strategy 40 eithre CN OR CP & what are its impact on MRP ?.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Check the configuration of VOV6 for schedule line category CN is not relevant for MRP whereas CP is relevant for MRP.

Schedule line category determines,  whether the system passes on requirements to materials requirements planning (MRP).

Best Regards,

R.Brahmankar

former_member261747
Contributor
0 Kudos

Hi Brahmankar

                             We were facing a problem where Sales order not consuming PIR. Then it is observed that sales order having Shedule line catagorey is CN After delivery. As per my understanding it should CP.

Am i right or wrong ?

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Schedule line category which is relevant for MRP appear in MD04 (transfer of requirements ) and will consume the PIR.

Please note schedule line category overrides the requirements class Setting

In VOV5 you can define the schedule line category for Item category and MRP type.

In VOV6 for this schedule line category, ensure the "Req. / Assembly" flag is ticked,


Best Regards,

R.Brahmankar