on 2010 Mar 31 9:11 AM
Hello
In make to order scenario, there are 2 schedule lines for the MTO item in create mode of Order. 0 confirm quantity on the req
When I save the order, i can see only one schedule line with confirm quantity 0.
Hi,
Make-to-order production is controlled by the requirements type. The requirements type is
determined on the basis of the MRP group and the strategy group in the material master record.
Create material by specifying item category group as 0001 = Make u2013 to u2013 order (Normal item)
In MM01 Basic data tab, General item category field [0001] = Make u2013 to u2013 order, 0002 for configurable
material
Make u2013 to u2013 order checking group for availability check should be [02] = Individual requirements in Sales:
General/Plant tab.
Go to VA01 and raise the sales order by specifying this material that we created in the previous step
Item category is TAK
Schedule line category = CP
Requirement type = KE [Sales order Header Procurement Requirement field]
KE = Individual customer order without consumption
(For standard items item category group = NORM)
System determines requirement type 041-order/delivery requirements. This requirement type points requirement
class where we can control whether the system has to carryout TOR, Availability check, and Product allocation
functions.
Hope this helps.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.