Schedule for Past

Former Member
0 Kudos
37

Dear Experts,

Need your help for this.

How can we see schedule for past in Project Planning Board.

With default settings it shows current schedule only.

We can adjust display with "Adapy time scale" "Adapt Graphic Area".

Then past schedule is also visible, but with compressed scale. We need normal scale display.

Option Settings-time axis assitant, With that unit is changed, it is still compressed scale.

Requirement is to see past schedule with normal display.

Please sugget, what to do.

Thanks & Regards,

SSanjay

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

in proj planning board, go to options, in the scheduling tab set

set the start date in past to say -50 etc

Former Member
0 Kudos

Dear Virendra,

Thanks.

That did not work, I gave start in the past 360 days, no change.

What worked is:

GO to options - planning board - planning period, give start date in the past.

Thanks, your hint was very useful.