Hi, i need to quarterly change the Harnesses price according to the copper escalation/de-scalation.

The schedule agreement contains around 200 harness (part number), i currently use ME32l (item condition, Gross price, New validity period then enter the new price) to modify each part number price & then repeat the same process for the next part number.

Is there a way to change multiple part at the same time? or to upload an excel sheet containing the new prices?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi,

The only standard option you have is via t-code MEKL Price Change Involving Vendor's Scheduling Agreements. The problem you have with this is that it changes by condition type based on a fixed percentage or absolute amount. Meaning that if your price changes varies depending on the item, then this report does not fit your requirement and the only option is to build a custom upload report.

Hope it helps.