on 2021 Jul 16 5:41 PM
Dear Gurus,
I have integration QM with EWM in s/4 hana. When we do the first gr in ewm, inspection lot will create in erp. But when we do another GR with the same batch and material but different PO in EWM, it will create another inspection. May i know how to avoid the second inspection lot from created for the same material and batch? Is there any setting that i need to do in EWM or ERP QM view? Appreciate your advise.
Thanks
Hi Saddiq
I believe you have decentralized EWM in S4 HANA which is connected to ERP system.
You could use the material master inspection set up setting called 'Control insLot' in the QM view. If this setting is changed to '2' An inspection lot for each material and batch the system creates only one inspection lot for each material and batch. This is applicable only for few inspection types like 01, 04, 05 and 08 lot origins.
Thanks
Chitra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
8 | |
7 | |
4 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.