cancel
Showing results for 
Search instead for 
Did you mean: 

SAP PP-

Former Member
0 Kudos
104

Hello SAP-Guruu2019s

Pls tell me the process flow for Repetitive Mfg.

Any comments welcome & Thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Repetative manufacturing is period based planning and not based on orders. Normally same products will be manufactured over longer period of time..products will not change frequently. Confirmation is from backflushing and settlement is through from product cost collector for the period. Confirmaton will be without ref to planned orders. Planned orders are sufficient to carry out shop floor activity. In master data production versions and cost collector is must where this is not mandatory in discreate.

You do these steps for rem production:

mm01 : Material Master

- MRP - 4 view you click rem

cs01 : Create Bom

cr01 : Create Work Center

ca21 : Create Rate Routing

mm02 : Prodn Version

md61 : Create PIR

mc74 : Transfer PIR to Demand

kkf6n : Create Product Cost Collector

mb1c : Create Stock

md02 : MRP run

mfbf : Rem Back Flush

The detailed sequence of T.Codes for REM including Std cost estimate.

Material master - MM01

BOM - CS01

Price Planning - KP26

Work Center - CR01

Rate Routing - CA21

Material Master Change, enter production version - MM02 (MRP 4 View)

Product Cost Collector - KKF6N

Costing - CK40N

Backflushing - MFBF

Regards,

R.Brahmankar

Answers (3)

Answers (3)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Did you get what you want? Please tell me what you required more?

Regards,

R.Brahmankar

Former Member
0 Kudos

Please close this thread , if you are ok with all ans.

Former Member
0 Kudos

Hi,

1. Create demand by MD61 or MD50 planning table

2. Run MRP by MD02

3. Check the stock req list in MD04

4. Do goods receipt by MIGO for raw material.

5. For FERT material do backflush confirmation by MFBF.

6. Check the stock in MMBE.

Note: goods issue will happen automatically by 261 mvt. Goods receipt by 131 mvt.

Material master, BOM, rate routing , Production version are required for REM. In MRP4 view tick repetetive Manufacturing & assign REM profile.

Regards,

Dharma

Former Member
0 Kudos

Create MM with REM tick in MRP 4 view

Create BOM

Create Rate Routing CA21

Create Production Verson C223

Create Wk Center CR01

Create REM Profile OSPT

Create Product cost collector KKF6N

Create Planned Order MD11

Backflush MFBF

Nilam -)