Hi Expert

Please explain d meaning of Cycle set in Maintenance plan..

Plz tell me d complete steps o fcreating Cycle set for maintenace plan

Thanks

Abhishek Vyas

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

Cycle sets are used for usage in Multiple counter plan ,if you want to perform preventive maintenance for equipment say of frequency as 200 hrs or once in 2 months.

then you should create cycle set using IP11Z ,there you can mention the hours strategy by maintaining HRS and for months for strategy based one .(but the unit used must be same for cycle set and the measuring point created for the equipment for counter based maintenance)

while creating the Multiple counter plan you can specify this cycle cet and create the maintenance plan,specify the link as AND or OR which means system will generate call object once the both conditions are met OR whichever comes first

regards

thyagarajan