If we activate reservation in material master and during production of any FG we needs to supply material in production table, That requires material calculate automatically in the C002 as per BOM

Now if we want to issue more than this in production can we do automatically or need to remove reservation .After that only we can issue more material.

I want more clarity related to it.

ameya_beri
Active Contributor

Hello,

The reservation generated by the production order Requirement qty on it, which is calculated as per the production order header quantity and BOM for the components. You can issue less than or more than required quantity during actual production. The excess component quantity consumed will contribute to variance on the production order.