Same work center being used in different routings

Former Member
0 Kudos

Hi

I have requirement like this:

Workcenter WC1 works in two shifts Shist A & B.

It is being used in two routings for different products X & Y.

Product X will be prodiced in shift A.

Product Y will be produced in Shift B.

How to schedule it for different shifts for different products.

Thankls in advance.

Regards

YMREDDY

Accepted Solutions (0)

Answers (3)

Answers (3)

siddheshwar_rajguru2
Active Participant
0 Kudos

HI,

As per Suhas if the work center is using in two shifts and for fix product then go for different work cenetr this is easy and indivudual cost tracking also possible. so that you will come toknow the efficiency of shift also.

Regards

Siddhesh

Former Member
0 Kudos

Hi

Asper Suhas, I can create two work centers . But physically there is only one work center . How can I create two work centers just because for usage in two different products.

Is it feasible to di like that.

As per Raj , I am not able to get the answer. Can Raj eloborate as to how it can be scheduled..

Reards

YMREDDY

Former Member
0 Kudos

Simple solution is assign two machine categories as capacities to this work center and define the available time for the shifts.

When you create the production order for A and B products then these capacities will be copied..here from change mode you can assign the capacity manually to production orders of A and B products as per the shifts.

Regards

TAJUDDIN

Former Member
0 Kudos

Hi Tajuddin

System will not allow to assign two machine categories to the same work center.

Pl. chk.

Regards

YMREDDY

Former Member
0 Kudos

Create 0001 and 0002 from customizing.

Former Member
0 Kudos

since workcentre is not working on the material based.

but the routing worked on the material based

give the shifting timing and the break timing in the work center alone

you have to select the matrl product x in the routing and the sequence of operation for the product is mentioned that the product that be there for the working in the

shift A .

product Y is to be sequenced to work at that w.c at shift B

Former Member
0 Kudos

Hi,

If this work center is being used for fix timing and fix product.

Then define it seperately one center in to two. For first shift create CW1 & for second shift CW2. Enter timings as per shifts, and use them seperately.

Regards,

Suhas