Hi team!!

your assistance will be highly appreciated

I have a sales order with 2 materials and when I want to do the delivery I can only do for item 110. (material type: ZPRD)

even this item is related to item 100 ( material type: Kmat) , i need to deliver this too, but is not possible since i get the following logs:

*No schedule lines due for delivery up to the selected date

  • order item 0000 -00100 , with incomplete delivery group 001

I made some changes and got:

  • Delivery group 001: Item 000100 contains no confirmed schedule lines - Message no. V1298

Could you please help me identify what is happening?

Thanks in advance.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

not resolved

JL23
Active Contributor
0 Kudos

go into VA02, go into detail of your item, goto the schedule tab

make sure you have a confirmed quantity there.

you see there as well the delivery date.

Make sure that the selection date in VL02N not smaller than your delivery date for your confirmed schedule line

Former Member
0 Kudos

I have dóne it but the confirmed quantity is : 0 , how can I change it?

thanks

JL23
Active Contributor
0 Kudos

click the atp check button, you should get another screen telling you when the material becoes available.

if you click there the checkmark next to the quantity, then sap will add a new line with the confirmed quantity at a different date