S4HC Manage Project Demand : Resource list is empty

weiwei_chong
Explorer
0 Kudos

Hi, 

I would like to add demand for resources for Project WBS created. I have created employee and assigned work agreements with the same company code for Project. 

However, in the app "Manage Project Demand" > Resources Demand > Resources Assignments > the list of resourcs is empty. How can I enable existing employees available as Resources for the project team?

View Entire Topic
Brendan_Ward
Advisor
Advisor
0 Kudos

Hello,

Have you maintained the cost center of the demand as per the SAP Help https://help.sap.com/docs/SAP_S4HANA_CLOUD/f369b2eff700401494ba6e7c9a573288/498a9f26e20e4f08a83dccff... which states:

Once you have maintained the cost center of your demand, you can assign one or more resources directly within the resource demand. Direct staffing is supported for internal employees whose primary employment is assigned to the same cost center as the demand that you want to staff.

Best Regards,