S_ALR_870135** REPORT DATA ERROR

0 Kudos
309

Hi experts,

I budgeted the WBS element from cj30.

I released the budget from CJ32.

But it comes as 0 in the S_ALR_87013560 report, you can see the screenshot.

View Entire Topic
Ken_Melching
Product and Topic Expert
Product and Topic Expert

In CJ30 go to Extras->Availability Control->Analysis and see what it says about your budget.

0 Kudos

it says "availability control is not enabled."

Ken_Melching
Product and Topic Expert
Product and Topic Expert

Looks like something is wrong with your Budget Profile. Check it in configuration.